Upgrades to process power and controls system.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 4 |
DATE | April 2004 - November 2005 |
Construction of a new 60 megawatt Co-generation facility including substation, hog fuel unloading and handling conveyors, power distribution, concentrator, cooling tower and precipitator, converting two existing boilers.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 50 |
DATE | June 2004 - April 2006 |
Construction of new coal mine including substation, crusher, preparation plant, materials handling conveyors, rail load-out and refuse bin.
CUSTOMER | Western Canadian Coal Corp., Robertson P & E, Inc. |
---|---|
PEAK WORKFORCE | 25 |
DATE | July 2005 - November 2007 |
Power and controls and DCS upgrade for Clean Fuels upgrade project, general plant upgrades.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 10 |
DATE | July 2005 - January 2006 |
Power and controls upgrades.
CUSTOMER | Duke Energy |
---|---|
PEAK WORKFORCE | 7 |
DATE | October 2005 - Februrary 2006 |
Power and Controls upgrade.
CUSTOMER | Spectra Energy |
---|---|
PEAK WORKFORCE | 12 |
DATE | October 2005 - February 2014 |
Installation of small diamond recovery plant process power and control systems.
CUSTOMER | BHP Billiton - Internation Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 8 |
DATE | February 2006 - December 2006 |
Head box replacement; electrical and instrumentation for high density system; bleach plant DCS migration; medium voltage switchgear replacement.
CUSTOMER | West Fraser Mills Ltd. |
---|---|
PEAK WORKFORCE | 30 |
DATE | January 2007 - May 2007 |
Construction of new coal mine services complex and installation of 2 MVA back-up generator system.
CUSTOMER | The Gisborne Group |
---|---|
PEAK WORKFORCE | 15 |
DATE | May 2007 - July 2008 |
Process power and controls system.
CUSTOMER | BHP Billiton - Internation Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 7 |
DATE | June 2007 - April 2008 |
Power and control modifications to existing audit plant systems.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 2 |
DATE | December 2007 |
Installation of electrical and instrumentation for new facility.
CUSTOMER | Baymag Inc. |
---|---|
PEAK WORKFORCE | 20 |
DATE | September 2008 - May 2009 |
Modification to 500 Kv switches and installation of new 500 Kv breakers.
CUSTOMER | Mutual Construction (2000) Ltd. |
---|---|
PEAK WORKFORCE | 5 |
DATE | September 2008 - November 2008 |
Installation of substation and wind farm towers and bases.
CUSTOMER | Earth First |
---|---|
PEAK WORKFORCE | 10 |
DATE | October 2008 - December 2010 |
Installation of new Crusher Building, new Mill Building, new Truck Shop, plant-wide fire alarm and power generation; complete instrumentation installations including calibration, commissioning, start-up assistance, maintenance and consulting services.
CUSTOMER | Yukon Zinc Corporation |
---|---|
PEAK WORKFORCE | 95 |
DATE | January 2009 - December 2011 |
Plant electrical upgrade including replacement of medium voltage transformers, replacement of MCCs, and replacement of existing power and motor control conduit distribution system.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 35 |
DATE | June 2009 - December 2010 |
Provide assistance to BC Hydro personnel for modifications to generator high voltage terminations.
CUSTOMER | Kamtech Services |
---|---|
PEAK WORKFORCE | 4 |
DATE | November 2010 - June 2011 |
Installation of Freshwater Reclaim system, commissioning, and start-up.
CUSTOMER | Similco Mines Ltd. |
---|---|
PEAK WORKFORCE | 12 |
DATE | March 2011 |
Installation of mill-wide fire alarm system.
CUSTOMER | Simplex Grinnell |
---|---|
PEAK WORKFORCE | 12 |
DATE | March 2011 - June 2011 |
Provide QA/QC personnel to gather data and develop reports.
CUSTOMER | The Gisborne Group |
---|---|
PEAK WORKFORCE | 5 |
DATE | March 2011 - June 2011 |
CWP LRU 014 - 015 - Electrical Installations.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 30 |
DATE | April 2011 - December 2011 |
Installation of mill-wide fire alarm system.
CUSTOMER | Simplex Grinnell |
---|---|
PEAK WORKFORCE | 8 |
DATE | April 2011 - December 2011 |
Electrical and instrumentation installations for heavy media coal processing facility.
CUSTOMER | Robers & Schaefer Company |
---|---|
PEAK WORKFORCE | 28 |
DATE | April 2011 - April 2012 |
Steam Plant DCS upgrade.
CUSTOMER | MacKenzie Pulp Corp. |
---|---|
PEAK WORKFORCE | 20 |
DATE | May 2011 - October 2011 |
Refuse recovery, raw coal system and lighting supply; wash plant extension.
CUSTOMER | Taggart Global |
---|---|
PEAK WORKFORCE | 25 |
DATE | June 2011 - November 2012 |
Electrical installations for Mill Security systems at all three Prince George mills.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 15 |
DATE | July 2011 - August 2011 |
Electrical and instrumentation installations for PM2 Upgrade.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 30 |
DATE | July 2011 - December 2011 |
Electrical and instrumentation installations for new Pressure Diffuser.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 10 |
DATE | July 2011 - March 2012 |
Site-wide electrical and instrumentation installations, new truck shop and administration facility.
CUSTOMER | Walter Energy, Western Coal Corp. |
---|---|
PEAK WORKFORCE | 12 |
DATE | July 2011 - April 2012 |
Electrical and instrumentation installations for evaporator upgrade.
CUSTOMER | MacKenzie Pulp Mill Corp. |
---|---|
PEAK WORKFORCE | 12 |
DATE | August 2011 - December 2011 |
Electrical and instrumentation installations for various construction and upgrade projects (truck scale and water chiller).
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 6 |
DATE | January 2012 - December 2012 |
Electrical and instrumentation installations for boiler feedwater.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | March 2012 - September 2012 |
Demolition of existing Chlorate III Rectifier - electrical.
CUSTOMER | Chemtrade Logisitics |
---|---|
PEAK WORKFORCE | 20 |
DATE | April 2012 - November 2012 |
Wastewater Contract 3A - Electrical and Instrumentation Installations.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 30 |
DATE | April 2012 - December 2012 |
Recovery boiler Re & Re, tertiary fan and precipitator ID fan - electrical and instrumentation installations.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | May 2012 - September 2012 |
Electrical Installations.
CUSTOMER | Dowland Industrial Works Ltd. |
---|---|
PEAK WORKFORCE | 6 |
DATE | June 2012 - April 2013 |
Powerhouses, substations and intake buildings - electrical and instrumentation installations.
CUSTOMER | Eaton Corporation |
---|---|
PEAK WORKFORCE | 15 |
DATE | June 2012 - June 2014 |
Installation of mill-wide fire alarm system.
CUSTOMER | Gisborne Industrial Construction Ltd. |
---|---|
PEAK WORKFORCE | 15 |
DATE | June 2012 - November 2013 |
Mine process expansion including site-wide fibre optic infrastructure; electrical and instrumentation installation of new Moly Plant and Brownfield areas.
CUSTOMER | Gibraltar Mine Ltd. |
---|---|
PEAK WORKFORCE | 80 |
DATE | August 2012 - July 2013 |
PM2 DCS Migration - Electrical and instrumentation installations.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 4 |
DATE | January 2013 - April 2014 |
Miscellaneous construction projects and upgrades - Electrical and instrumentation installations.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 10 |
DATE | January 2013 - December 2013 |
Amine upgrade; Boilerhouse and DCS upgrade - Electrical and Instrumentation installations.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 25 |
DATE | March 2013 - December 2013 |
Mine expansion project.
CUSTOMER | Gisborne Industrial Contractors |
---|---|
PEAK WORKFORCE | 15 |
DATE | March 2013 - August 2013 |
Recovery Boiler Re & Re - Electrical and instrumentation installations.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | May 2013 - June 2013 |
Installation of network and fibre optic control system; commissioning of plant and process equipment.
CUSTOMER | Thompson Creek Metals |
---|---|
PEAK WORKFORCE | 8 |
DATE | July 2013 - December 2014 |
Commissioning assistance of plant process equipment and start up.
CUSTOMER | Thomspon Creek Metals |
---|---|
PEAK WORKFORCE | 30 |
DATE | July 2013 - December 2014 |
Genset Install.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 8 |
DATE | August 2013 - December 2013 |
Electrical installations for Depot upgrade.
CUSTOMER | Ridgeview Construction |
---|---|
PEAK WORKFORCE | 6 |
DATE | September 2013 - March 2014 |
Electrical and instrumentation - Bleach Plant and Brown Stock DCS upgrade.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 24 |
DATE | April 2014 - September 2014 |
Electrical installations for medium voltage MCC 5 Kv replacement.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 32 |
DATE | April 2014 - September 2014 |
Electrical installations for medium voltage MCC 5 Kv replacement.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 32 |
DATE | April 2014 - September 2014 |
Lignin Recovery Plant - Electrical and instrumentation installations.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 8 |
DATE | April 2014 - December 2014 |
Electrical and instrumentation installations for Cooling Water upgrade.
CUSTOMER | The Gisborne Group |
---|---|
PEAK WORKFORCE | 5 |
DATE | July 2014 - July 2015 |
Electrical and instrumentation installations for load bank.
CUSTOMER | CIMS Limited Partnership |
---|---|
PEAK WORKFORCE | 10 |
DATE | August 2014 - November 2014 |
Instrumentation maintenance support.
CUSTOMER | MacKenzie Pulp Mill Corp. |
---|---|
PEAK WORKFORCE | 4 |
DATE | September 2014 - May 2015 |
Electrical and instrumentation installations for Phase I and II of Genset installation.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 10 |
DATE | September 2014 - August 2015 |
Electrical and instrumentation installations for steam turbine generator upgrade.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | November 2014 - April 2015 |
Electrical and instrumentation installations for fire alarm system.
CUSTOMER | Tyco - Simplex Grinnell |
---|---|
PEAK WORKFORCE | 10 |
DATE | November 2014 - April 2015 |
Underground electrical and instrumentation expansion.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 7 |
DATE | January 2015 - present |
Electrical installations for Powerhouse upgrades and gensets.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 7 |
DATE | January 2015 - present |
Electrical installations for Powerhouse upgrades and gensets.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 7 |
DATE | January 2015 - present |
Electrical installations, data installations, security system installation.
CUSTOMER | New Haven Construction |
---|---|
PEAK WORKFORCE | 8 |
DATE | March 2015 - present |
Electrical and instrumentation installations for Phase II of Lignin recovery plant.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 10 |
DATE | March 2015 - present |
Electrical and instrumentation installations for upgrades to steam plant.
CUSTOMER | MacKenzie Pulp Mill Corp. |
---|---|
PEAK WORKFORCE | 10 |
DATE | August 2015 - present |
Electrical installations for new hotel complex.
CUSTOMER | IDL Projects Inc. |
---|---|
PEAK WORKFORCE | 8 |
DATE | August 2015 - present |
Electrical installations for phase II of apartment/condominium complex.
CUSTOMER | 0999942 BC Ltd. |
---|---|
PEAK WORKFORCE | 6 |
DATE | August 2015 - August 2017 |
Installation of underground utilities and street lighting.
CUSTOMER | Klein & Sons Ltd. |
---|---|
PEAK WORKFORCE | 4 |
DATE | Fall 2015 (expected) |
Building Canada’s next Gold Mine. Primary Crusher, conveying systems, ADR commissioning, secondary/tertiary crushing facility, Gold recovery plant.
190630-VIT-Eagle-Update Early July(1) from Adnet Communications Inc. on Vimeo .
CUSTOMER | Victoria Gold |
---|---|
PEAK WORKFORCE | 70 |
DATE | September 2018 - ongoing |