Ekati Diamond Mine - Processing Plant - Northwest Territories

Upgrades to process power and controls system.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 4
DATE April 2004 - November 2005

Canfor - PG Pulp Co-Gen Project - Prince George, BC

Construction of a new 60 megawatt Co-generation facility including substation, hog fuel unloading and handling conveyors, power distribution, concentrator, cooling tower and precipitator, converting two existing boilers.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 50
DATE June 2004 - April 2006

Wolverine Coal - New Coal Mine - Tumbler Ridge, BC

Construction of new coal mine including substation, crusher, preparation plant, materials handling conveyors, rail load-out and refuse bin.

CUSTOMER Western Canadian Coal Corp., Robertson P & E, Inc.
PEAK WORKFORCE 25
DATE July 2005 - November 2007

Husky Energy - Clean Fuels Upgrade - Prince George, BC

Power and controls and DCS upgrade for Clean Fuels upgrade project, general plant upgrades.

CUSTOMER Husky Energy
PEAK WORKFORCE 10
DATE July 2005 - January 2006

Duke Energy - Compressor Stations and Processing Plants - Various locations, BC

Power and controls upgrades.

CUSTOMER Duke Energy
PEAK WORKFORCE 7
DATE October 2005 - Februrary 2006

Spectra Energy - Compressor Stations and Processing Plants - Various locations, BC

Power and Controls upgrade.

CUSTOMER Spectra Energy
PEAK WORKFORCE 12
DATE October 2005 - February 2014

Ekati Diamond Mine - Small Diamond Recovery - Northwest Territories

Installation of small diamond recovery plant process power and control systems.

CUSTOMER BHP Billiton - Internation Quest Engineering Ltd.
PEAK WORKFORCE 8
DATE February 2006 - December 2006

West Fraser Mills - Hinton Pulp Mill - Hinton, AB

Head box replacement; electrical and instrumentation for high density system; bleach plant DCS migration; medium voltage switchgear replacement.

CUSTOMER West Fraser Mills Ltd.
PEAK WORKFORCE 30
DATE January 2007 - May 2007

Wolverine Coal Mine - Services Complex - Tumbler Ridge, BC

Construction of new coal mine services complex and installation of 2 MVA back-up generator system.

CUSTOMER The Gisborne Group
PEAK WORKFORCE 15
DATE May 2007 - July 2008

Ekati Diamond Mine - Glycol Heat Recovery - Northwest Territories

Process power and controls system.

CUSTOMER BHP Billiton - Internation Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE June 2007 - April 2008

Diavik Diamond Mine - Audit Plant Modifications - Northwest Territories

Power and control modifications to existing audit plant systems.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 2
DATE December 2007

Baymag Plant II - Calcining Facility Phase 2A - Canmore, AB

Installation of electrical and instrumentation for new facility.

CUSTOMER Baymag Inc.
PEAK WORKFORCE 20
DATE September 2008 - May 2009

BC Hydro - Williston Substation - Prince George, BC

Modification to 500 Kv switches and installation of new 500 Kv breakers.

CUSTOMER Mutual Construction (2000) Ltd.
PEAK WORKFORCE 5
DATE September 2008 - November 2008

Dokie Wind Farm Project - Chetwynd, BC

Installation of substation and wind farm towers and bases.

CUSTOMER Earth First
PEAK WORKFORCE 10
DATE October 2008 - December 2010

Wolverine Mine - New Facilities - Yukon Territories

Installation of new Crusher Building, new Mill Building, new Truck Shop, plant-wide fire alarm and power generation; complete instrumentation installations including calibration, commissioning, start-up assistance, maintenance and consulting services.

CUSTOMER Yukon Zinc Corporation
PEAK WORKFORCE 95
DATE January 2009 - December 2011

Husky Energy - Plant Electrical Upgrade - Prince George, BC

Plant electrical upgrade including replacement of medium voltage transformers, replacement of MCCs, and replacement of existing power and motor control conduit distribution system.

CUSTOMER Husky Energy
PEAK WORKFORCE 35
DATE June 2009 - December 2010

BC Hydro - Generator Modifications - Aberfeldie Dam Site, BC

Provide assistance to BC Hydro personnel for modifications to generator high voltage terminations.

CUSTOMER Kamtech Services
PEAK WORKFORCE 4
DATE November 2010 - June 2011

Copper Mountain - Freshwater Reclaim - Princeton, BC

Installation of Freshwater Reclaim system, commissioning, and start-up.

CUSTOMER Similco Mines Ltd.
PEAK WORKFORCE 12
DATE March 2011

Copper Mountain - Fire Alarm - Princeton, BC

Installation of mill-wide fire alarm system.

CUSTOMER Simplex Grinnell
PEAK WORKFORCE 12
DATE March 2011 - June 2011

Copper Mountain - QA / QC - Princeton, BC

Provide QA/QC personnel to gather data and develop reports.

CUSTOMER The Gisborne Group
PEAK WORKFORCE 5
DATE March 2011 - June 2011

Husky Energy - Load Rack Upgrade - Prince George Refinery - Prince George, BC

CWP LRU 014 - 015 - Electrical Installations.

CUSTOMER Husky Energy
PEAK WORKFORCE 30
DATE April 2011 - December 2011

Endako / Thompson Creek Mine - Fire Alarm - Endako, BC

Installation of mill-wide fire alarm system.

CUSTOMER Simplex Grinnell
PEAK WORKFORCE 8
DATE April 2011 - December 2011

Elkview Mine - Heavy Media Coal Processing - Fernie, BC

Electrical and instrumentation installations for heavy media coal processing facility.

CUSTOMER Robers & Schaefer Company
PEAK WORKFORCE 28
DATE April 2011 - April 2012

MacKenzie Pulp Corp. - DCS Upgrade - MacKenzie, BC

Steam Plant DCS upgrade.

CUSTOMER MacKenzie Pulp Corp.
PEAK WORKFORCE 20
DATE May 2011 - October 2011

Willow Creek Minesite - Refuse, Raw Coal, Lighting - Chetwynd, BC

Refuse recovery, raw coal system and lighting supply; wash plant extension.

CUSTOMER Taggart Global
PEAK WORKFORCE 25
DATE June 2011 - November 2012

Canfor - Northwood, PG Pulp, Intercon Security System - Prince George, BC

Electrical installations for Mill Security systems at all three Prince George mills.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 15
DATE July 2011 - August 2011

Hinton Pulp Mill - PM2 Upgrade - Hinton, AB

Electrical and instrumentation installations for PM2 Upgrade.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 30
DATE July 2011 - December 2011

Hinton Pulp Mill - New Pressure Diffuser - Hinton, AB

Electrical and instrumentation installations for new Pressure Diffuser.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 10
DATE July 2011 - March 2012

Brule Mine - New Truck Shop / Admin Building - Chetwynd, BC

Site-wide electrical and instrumentation installations, new truck shop and administration facility.

CUSTOMER Walter Energy, Western Coal Corp.
PEAK WORKFORCE 12
DATE July 2011 - April 2012

MacKenzie Pulp Corp. - Evaporator Upgrade - MacKenzie, BC

Electrical and instrumentation installations for evaporator upgrade.

CUSTOMER MacKenzie Pulp Mill Corp.
PEAK WORKFORCE 12
DATE August 2011 - December 2011

Hinton Pulp Mill - Truck Scale & Water Chiller - Hinton, AB

Electrical and instrumentation installations for various construction and upgrade projects (truck scale and water chiller).

CUSTOMER West Fraser Mills
PEAK WORKFORCE 6
DATE January 2012 - December 2012

Canfor - PG Pulp Boiler Feedwater - Prince George, BC

Electrical and instrumentation installations for boiler feedwater.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE March 2012 - September 2012

Chemtrade Logistics - Chlorate III Rectifier - Prince George, BC

Demolition of existing Chlorate III Rectifier - electrical.

CUSTOMER Chemtrade Logisitics
PEAK WORKFORCE 20
DATE April 2012 - November 2012

Husky Energy - Wastewater Treatment - Prince George, BC

Wastewater Contract 3A - Electrical and Instrumentation Installations.

CUSTOMER Husky Energy
PEAK WORKFORCE 30
DATE April 2012 - December 2012

Canfor - PG Pulp Recovery Boiler - Prince George, BC

Recovery boiler Re & Re, tertiary fan and precipitator ID fan - electrical and instrumentation installations.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE May 2012 - September 2012

Dasque Cluster Hydro-Electrical Project - Terrace, BC

Electrical Installations.

CUSTOMER Dowland Industrial Works Ltd.
PEAK WORKFORCE 6
DATE June 2012 - April 2013

Middle & Dasque Creek Powerhouse - Terrace, BC

Powerhouses, substations and intake buildings - electrical and instrumentation installations.

CUSTOMER Eaton Corporation
PEAK WORKFORCE 15
DATE June 2012 - June 2014

Mt. Milligan - Fire Alarm System - Mt. Milligan, BC

Installation of mill-wide fire alarm system.

CUSTOMER Gisborne Industrial Construction Ltd.
PEAK WORKFORCE 15
DATE June 2012 - November 2013

Gibraltar Mine Ltd. - GDP3 Project - McLeese Lake, BC

Mine process expansion including site-wide fibre optic infrastructure; electrical and instrumentation installation of new Moly Plant and Brownfield areas.

CUSTOMER Gibraltar Mine Ltd.
PEAK WORKFORCE 80
DATE August 2012 - July 2013

Hinton Pulp Mill - PM2 DCS Migration - Hinton, AB

PM2 DCS Migration - Electrical and instrumentation installations.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 4
DATE January 2013 - April 2014

Hinton Pulp Mill - Various Upgrades - Hinton, AB

Miscellaneous construction projects and upgrades - Electrical and instrumentation installations.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 10
DATE January 2013 - December 2013

Husky Energy - Boilerhouse House Electrical Upgrade - Prince George, BC

Amine upgrade; Boilerhouse and DCS upgrade - Electrical and Instrumentation installations.

CUSTOMER Husky Energy
PEAK WORKFORCE 25
DATE March 2013 - December 2013

LIM - Labrador Iron Mine - Nfld & Labrador

Mine expansion project.

CUSTOMER Gisborne Industrial Contractors
PEAK WORKFORCE 15
DATE March 2013 - August 2013

Canfor - Northwood Pulp - Prince George, BC

Recovery Boiler Re & Re - Electrical and instrumentation installations.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE May 2013 - June 2013

Mt. Milligan - Thompson Creek Metals - Mt. Milligan, BC

Installation of network and fibre optic control system; commissioning of plant and process equipment.

CUSTOMER Thompson Creek Metals
PEAK WORKFORCE 8
DATE July 2013 - December 2014

Mt. Milligan - Thompson Creek Metals - Mt. Milligan, BC

Commissioning assistance of plant process equipment and start up.

CUSTOMER Thomspon Creek Metals
PEAK WORKFORCE 30
DATE July 2013 - December 2014

DeBeers - Snap Lake Diamond Mine - Snap Lake, Northwest Territories

Genset Install.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 8
DATE August 2013 - December 2013

Bandstra Trucking - Depot Upgrade - Prince George, BC

Electrical installations for Depot upgrade.

CUSTOMER Ridgeview Construction
PEAK WORKFORCE 6
DATE September 2013 - March 2014

Hinton Pulp Mill - DCS Upgrade - Hinton, AB

Electrical and instrumentation - Bleach Plant and Brown Stock DCS upgrade.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 24
DATE April 2014 - September 2014

Hinton Pulp Mill - MCC 5 Kv Replacement - Hinton, AB

Electrical installations for medium voltage MCC 5 Kv replacement.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 32
DATE April 2014 - September 2014

Hinton Pulp Mill - MCC 5 Kv Replacement - Hinton, AB

Electrical installations for medium voltage MCC 5 Kv replacement.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 32
DATE April 2014 - September 2014

Hinton Pulp Mill - Lignin Recovery Plant Phase I - Hinton, AB

Lignin Recovery Plant - Electrical and instrumentation installations.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 8
DATE April 2014 - December 2014

BC Hydro - Bridge River Power Project - Bridge River, BC

Electrical and instrumentation installations for Cooling Water upgrade.

CUSTOMER The Gisborne Group
PEAK WORKFORCE 5
DATE July 2014 - July 2015

Spectra Energy - Load Bank - Port Coquitlam, BC

Electrical and instrumentation installations for load bank.

CUSTOMER CIMS Limited Partnership
PEAK WORKFORCE 10
DATE August 2014 - November 2014

MacKenzie Pulp Mill - Maintenance - MacKenzie, BC

Instrumentation maintenance support.

CUSTOMER MacKenzie Pulp Mill Corp.
PEAK WORKFORCE 4
DATE September 2014 - May 2015

Genalta Power - Genset Installation Phase I & II - Peace River, BC

Electrical and instrumentation installations for Phase I and II of Genset installation.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 10
DATE September 2014 - August 2015

Canfor - Intercon Steam Turbine Generator - Prince George, BC

Electrical and instrumentation installations for steam turbine generator upgrade.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE November 2014 - April 2015

Red Chris Mine - Fire Alarm - Dease Lake, BC

Electrical and instrumentation installations for fire alarm system.

CUSTOMER Tyco - Simplex Grinnell
PEAK WORKFORCE 10
DATE November 2014 - April 2015

De Beers Canada - Underground Expansion - Snap Lake, Northwest Territories

Underground electrical and instrumentation expansion.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE January 2015 - present

De Beers Canada - Powerhouse Upgrades - Snap Lake, Northwest Territories

Electrical installations for Powerhouse upgrades and gensets.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE January 2015 - present

De Beers Canada - Powerhouse Upgrades - Snap Lake, Northwest Territories

Electrical installations for Powerhouse upgrades and gensets.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE January 2015 - present

Nadleh Whut'en First Nations - Multicultural Center - Fort Fraser, BC

Electrical installations, data installations, security system installation.

CUSTOMER New Haven Construction
PEAK WORKFORCE 8
DATE March 2015 - present

Hinton Pulp Mill - Lignin recovery Phase II - Hinton, AB

Electrical and instrumentation installations for Phase II of Lignin recovery plant.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 10
DATE March 2015 - present

MacKenzie Pulp Mill - Steam Plant Upgrade - MacKenzie, BC

Electrical and instrumentation installations for upgrades to steam plant.

CUSTOMER MacKenzie Pulp Mill Corp.
PEAK WORKFORCE 10
DATE August 2015 - present

Home2 Suites by Hilton - New Hotel - Fort St. John, BC

Electrical installations for new hotel complex.

CUSTOMER IDL Projects Inc.
PEAK WORKFORCE 8
DATE August 2015 - present

Magnolia Gardens - Phase II - Prince George, BC

Electrical installations for phase II of apartment/condominium complex.

CUSTOMER 0999942 BC Ltd.
PEAK WORKFORCE 6
DATE August 2015 - August 2017

City of Prince George - Rec Place Expansion - Prince George, BC

Installation of underground utilities and street lighting.

CUSTOMER Klein & Sons Ltd.
PEAK WORKFORCE 4
DATE Fall 2015 (expected)

Eagle Gold Project

Building Canada’s next Gold Mine. Primary Crusher, conveying systems, ADR commissioning, secondary/tertiary crushing facility, Gold recovery plant.

190630-VIT-Eagle-Update Early July(1) from Adnet Communications Inc. on Vimeo .

CUSTOMER Victoria Gold
PEAK WORKFORCE 70
DATE September 2018 - ongoing

24 HOUR EMERGENCY SERVICE
250.563.4100 • CLASS A LICENSED & BONDED